|

   



    
|

If you are a
contractor, developer or excavating company, please note the following
requirements:
Construction of Public Water and
Sewer Mains
-
It shall be a violation of District
policy for any person to construct a water and/or sanitary sewer main
within the jurisdiction of the Board without first having an executed
Conveyance and Acceptance form.
-
All water and sewer main extensions
within the jurisdiction of the Board shall be made under the
supervision of the District Engineer in accordance with the
District’s specifications.
-
Those areas of the District located
west of Simms Street to the hogback are subject to specific bedding
and pipe material requirements as detailed in District construction
specifications.
-
A Performance and Maintenance Bond
equal to 100% of the contract (or construction cost) shall be
furnished by the contractor to the District on all water and sewer
main construction in the District.

Water System - General Requirements:
-
All plans for water main
extensions, improvements and changes shall be submitted to the
District Engineer. All plans must be reviewed by the District Manager
and the Denver Water Department.
-
No taps will be allowed, nor tap
permits issued, until construction has been preliminarily accepted by
the District.
-
Plans to be reviewed must be
accompanied by a minimum of six (6) sets of the recorded plat(s). Two
copies shall be retained by the District Manager, one copy delivered
to the District Engineer, one copy delivered to the District’s
Attorney, and two copies delivered to the Denver Water Department.
-
If any water main is to be
constructed outside of a public right-of-way, the construction plans
must be accompanied by a request for acceptance of a water easement in
accordance with Article XX of these specifications.
-
A pre-construction meeting must be
arranged by the contractor and held prior to the start of any work.
The District Engineer, District Manager, contractor, and owner or
owner's engineer must be represented at this meeting. The meeting
shall be held at the District office at 9850B West Girton Drive,
Lakewood, CO 80227 or at such place as the District Manager shall
direct.
-
All contractors must notify the
District Engineer and District Manager at least 48 hours prior to the
start of construction.
-
Approved plans and a copy of the
specifications must be kept on the job site by the contractor at all
times.
-
Cross connection control shall be
enforced in accordance with the Colorado State Department of Health's
publication entitled, "Cross Connection Control", latest revision.
-
No work shall be backfilled
(including bedding material above the springline of the pipe) until
construction has been reviewed for compliance by the District Engineer.
Return
to Top

SEWER SYSTEM -
GENERAL REQUIREMENTS:
-
All plans for sewer main extensions,
improvements and revisions shall be submitted to the District Engineer.
All plans must be reviewed by the District Manager and the District
Engineer.
-
No taps will be allowed, nor
tap permits issued, until construction has been preliminarily accepted
by the District or approved for preliminary acceptance by the District
Engineer.
-
Plans to be reviewed must be
accompanied by four (4) sets of the recorded plat(s). Two copies shall
be retained by the District Manager, One copy delivered to the District
Engineer and one copy delivered to the District’s Attorney.
-
If any sewer main is to be
constructed outside of a public right-of-way, the construction plans
must be accompanied by a request for acceptance of a sewer easement in
accordance with Article XXI of these specifications.
-
A pre-construction meeting must
be arranged by the contractor and held prior to the start of any work.
The District Engineer, District Manager, contractor and owner or owner's
engineer must be represented at this meeting. The meeting shall be held
at the District office at 9850B W. Girton Dr., Lakewood, Colorado 80227,
or at such place as the District Manager shall direct.
-
All contractors must notify the
District Engineer and District Manager at least 48 hours prior to the
start of construction.
-
Approved plans and a copy of
the specifications must be kept on the job site by the contractor at all
times. The contractor shall maintain a marked up set of plans showing
any variations of the contract drawings. These as-built drawings shall
be presented to the District Engineer prior to final testing and
acceptance of the sewer line.
-
No work shall be
backfilled (including bedding material above the springline of the pipe)
until construction has been reviewed for compliance by the District
Engineer.

Use of Public
Water and Sewer Systems
-
The observation fee for water
and sewer main connections shall be as provided on the attached
Schedule of Fees. No work shall start until all District fees
have been paid. No work shall start until the District office has
been properly notified.
-
All cost and expense incidental
to the installation and connection of the water or sewer service shall
be borne by the landowner, subdivider or developer who shall indemnify
the Board for any loss, damage, or attorney’s fees that may directly or
indirectly be occasioned by the installation of the water or sewer
service. No inspections, field testing, construction observation or
other work shall be done by the District on Saturdays, Sundays or
holidays unless permission is granted by the District Manager.
-
The owner of the house,
apartment or buildings of any nature shall be responsible for repair and
upkeep of the sewer or water service lines from the street side of the
meter pit to the structure in cases of water service, and from the main
to the structure in cases of sewer service.
-
The water service line shall be
soft type K copper. Fittings shall be brass or copper alloy. Where
meters are to be set in driveways, parking lots or other paved areas,
prior approval will be required. Connections shall be by "flared"
methods.
-
The sewer service line shall be
PVC pipe with push on joints or any other material approved by the Board
of Directors, subject to the limitations of the Uniform Plumbing Code
requirements. The line shall be watertight and on a constant grade in a
straight line, and not closer than five horizontal feet from any bearing
wall, except where it exits the building.
-
The water service shall be
brought to the building at an elevation that will allow a minimum of
four and one-half feet of cover over the top of the pipe. No service
shall be laid parallel to or within five horizontal feet of any bearing
wall. The water service line shall generally be laid at a uniform grade
and in a straight and continuous line. In those cases where, due to the
length of the service line, it is impossible to have a service line
without a joint, the jointing method will be submitted for review by the
District.
-
All excavations required for
the installation of a water or sewer service shall be open trench work
unless otherwise approved. Pipe laying and backfill shall be performed
in accordance with the standard specifications adopted by the Denver
Board of Water Commissioners and the District.
-
The applicant for the building
water and/or sewer service permit shall notify the District when the
service is ready for inspection and connection. (Note: the District
should also inspect this connection). The work on water or sewer service
lines shall be done by approved plumbers or utilities contractors
subject to District inspection, but plumbing work contracted for by an
approved plumber may be performed by him through journeyman plumbers or
apprentices under his direct supervision but must meet the Colorado
State Department of Health's Technical Plumbing Code.
-
Revocation of Plumber's or Utility
Contractor's Approval: The violation of any of these Rules and
Regulations or the District's installation specifications shall
constitute sufficient grounds for revocation of the plumber's or utility
contractor's right to continue to work within the District.
Whenever it appears a violation has been committed, the plumber or
utility contractor shall be sent written notice of hearing.
-
All water and sewer service
lines installed within the area under jurisdiction of the Board shall be
done only by approved plumbers and contractors with applicable licenses
to do work within the area. Liability insurance shall be carried in
sufficient amounts to protect the District against any and all claims
that may be occasioned by the work of the plumber or contractor.
Worker's Compensation Insurance shall be carried in accordance with the
provisions of the State of Colorado.
-
All contractors, plumbers and
others doing work on any water or sewer main, service lines or
structures in the District shall comply with applicable District,
Jefferson County, Denver or State Highway Department regulations on
excavation, backfill, compaction and restoration or surfacing.
-
All construction work and
materials shall meet the standards and specifications of the Willowbrook
Water and Sanitation District, The Metro Wastewater Reclamation
District, the Denver Board of Water Commissioners and the Technical
Plumbing and Building Codes of the Colorado Department of Public Health
and Environment. The District's specifications may be obtained at the
office of the District Engineer. The District's specifications may be
more strict than those of other regulatory agencies and shall govern in
instances of conflict.
-
All permits, fees and licenses
shall be paid for by the contractor, plumber or others doing work in the
District prior to the start of construction.
-
All construction of sewer and
water facilities shall be adequately guarded with barricades and lights
so as to protect the public from hazard. Street, sidewalks, parkways
and other public or private property disturbed in the course of the work
shall be restored in a manner satisfactory to the District within a
reasonable time.
-
Swimming Pools and Hot Tubs:
No public or private swimming pool or hot tub drain shall be connected
to the sanitary sewer system. The District does not allow discharge
from a swimming pool or a hot tub into it's sanitary sewer system except
for filter system effluent as approved on an individual basis.
-
The District shall not allow
any sub-drain, foundation or groundwater system to be installed within
it's water or sewer line trenches and will not allow any drainage system
to be connected to it's water or sewer system (bedding, trench) or water
or sewer lines in any manner whatsoever.
-
It shall be unlawful for anyone
to discharge any waste or byproducts into the sanitary sewer system
other than normal effluent. Anyone desiring to discharge other than
normal effluent, as defined by Denver Metro Reclamation District,
shall be required to obtain a special permit from the District.
Instances of special permits include discharge of toxic materials,
purging of mobile home holding tanks, dumping of used oils, paint,
gasoline, solvents and other petroleum based products.
Return
to Top
Application
for Service and Charges

-
All properties requiring water
and sewer service shall pay the applicable fees charged by Denver, the
Lakehurst Water and Sanitation District, the Metro Wastewater
Reclamation District and the District.
-
Special Water Service through
Fire Hydrants: If temporary water service is supplied through a fire
hydrant, a permit for the use of the hydrant shall be obtained from the
District by application. A deposit will be required to cover water
meter and fire hydrant damage and estimated water bill. All special
contracts using water through fire hydrants shall desist during the
duration of any fire in the District, or upon request by the District
for any reason.
-
All hydrant water users shall have a
permit from the District. All water used from hydrants will be
metered or billed per load. Any damage to the hydrant meter or
District property will be paid for by the permittee. All hoses and
connections shall be accordance with Colorado Health Department
criteria.
-
Sewer Services - General: No
connection to a Willowbrook Water and Sanitation District owned sewer
main, or approved stub out, shall be allowed prior to the purchase of a
District tap permit and payment of appropriate Metropolitan Wastewater
Reclamation District fees. Sewer service lines shall be installed in a
separate trench, maintaining a ten-foot horizontal separation from the
water service line. All sewer service installation shall be in
accordance with the specifications of the Willowbrook Water and
Sanitation District, Uniform Plumbing and Building Codes, Metropolitan
Wastewater Reclamation District and Jefferson County Building
Department.
-
Tap permits and/or physical
connection permits will not be allowed prior to District preliminary
acceptance of the sewer main to be tapped.
Sewer Service - Ownership
and Maintenance
Ownership - The sewer
service line, including the connection to the District's main, shall be
owned by and installed at the expense of the owner of the property to be
served.
Inspections
- No taps or connections will be allowed to the District's mains unless
a District representative is present to inspect the connection. Dye
tests will be required on all sewer service connections. Subject to
Section 602, no inspections will be made unless a 24-hour notice during
normal business hours has been received by the District. All taps must
be made in accordance with District specifications.
Grease Traps - In all cases where grease traps or other
filtering processes are required to be inspected, the owner and/or
operator shall maintain a log, signed by the contractor, of each time
the device is cleaned and/or maintained. This log shall be available
for inspection by the District. All grease traps shall be cleaned with
sufficient regularity to prevent grease buildup in the District's sewer
system. Failure to adequately maintain a grease trap or other filtering
device, which results in grease buildups in the District's sewer system,
will result in the District charging the offending property owner/tenant
the cost of cleaning the affected sewer mains.
Sump Pump
- No sump pump shall be connected or discharged into the sanitary sewer
system. The District may require inspection of all SUMP pumps to insure
proper installation and daylighting.
Return to Top
|